Leila Lake House Project
Pictures of our house
construction project started in May of 2003. We purchased the land from a
couple who live in Oregon and decided to sell this one of a kind lot in the
Eureka Area. We had the tundra scraped from the house building site in the
fall of 2001 and began the site work in May of 2003. From Victory, Lee Althens
did the foundation and framing. Pat Causey from Glacier
View did the dozer work. Ed Farmer from Nelchina is did the backhoe work and
hauled lots of
gravel. The foundation started June 16 with the
framing package arriving a day later. Had only a few problems so far with
the trusses for the second floor not matching up with the 10/12 pitch
trusses and a mix up with a few of the window sizes. The siding took a month
longer to get than originally anticipated but other than that everything has
gone fairly smooth thanks to Lee.
Click on
an image for larger photo: |
Site Work |
Problem
low spot raised in the driveway. Hired Pat Causey to knock down a high spot with his cat and
raise a low spot in the driveway. |
Initial
dozer work to level house site. Pat dug down approximately 2 feet. Later we
dug down an additional foot and backfilled with 10" of D1 gravel for better
drainage. |
View
of house site looking east toward the Chugach Mountains. |
Ken
Butters and Doug walking site after dozer work discussing the site and soil
conditions. |
Foundation & First Floor |
Footings
in and foundation built June 20, 2003. |
Eddie
Farmers son backfilling the foundation while Eddie hauls gravel. Blueboard
insulation installed on foundation. |
First
3 walls up June 24, 2003. Lee Althens nailing top plate together. Dozer
backfilling below. |
View
of framing material for first and second floors. |
First
three walls viewed from side facing lake. |
Third
wall going up. Tyler Althens in foreground with Ryan Beachy in background. |
Second Floor Goes UP |
The
second floor gets framed up for the master bedroom and loft overlooking the
downstairs. |
Me
standing in the opening for the french doors facing the lake. |
Another
view of the framing with the second floor done, waiting for trusses, July 6,
2003. |
|
Trusses
& Roof |
View
from Glenn highway June 24, 2003. |
July
26, 03 Trusses up - View from lake (east elevation). |
Outhouse
walls build and ready to go up. June 24, 2003. |
July
26, 03 View from West (west elevation) |
View
from North July 26, 03 (north elevation) |
View
from the highway side (west). |
View
from upstairs loft looking towards the lake (east). |
View
from the lake side (east). |
The
roof and windows are completed! Viewed from the driveway (east). |
View
from Glenn Highway July 26, 03 |
|
The
house from the road with our lake in the background, early August. |
Outhouse Progress |
Outhouse
foundation June 23, 2003. Required until I figure out a water and septic
system. |
Donna
pounding nails. Putting on the siding July 5, 2003. |
Doug
getting ready to work on the roof rafters. |
The
roof almost finished. |
Roof
on ready for the door and the inspector. |
The
building inspector arrives! Warren Garner takes a tour of the structure
checking it out. |
Almost
complete - the Seriously over engineered outhouse! Donna used vinyl flooring
tiles and we used a laminated counter for the bench. Electric lights & heat. |
Meditation
in the outhouse. If an outhouse took this long we'll never get the house
done! |
Misc |
Checking
the survey lines. |
View
from the first power pole after two days of Donna & I brushing out 900' of
easement for the power line. Lots of work! |
Cow
moose checking on the house progress July 27, 2003. |
In
the dining room contemplating the project and enjoying the view of the lake
and mountains during a warm sunny August day. |
Oct 2003 Trying
to Beat the Weather |
Copper
Valley Electric Assoc getting the first of 5 poles ready. This is the pole
the transformer and meter were installed on. |
CVEA
places the first power pole. |
Ed
Farmer digging the final bit of trench to lay the 4/0 service entrance cable
from the pole to the house. Ed's Cat had to dig thru 8" of frost! |
Finished
the deck. We got 3" of snow while trying to get the deck finished. |
Main
entry porch and steps finished. Took a couple of weekends to figure out how
we wanted the front steps. |
Donna
& I built the stand for the fuel tank and I finally
got the railing built for the upstairs porch and didn't even fall off while
working on it! |
Feb 2005 |
Finished
the siding with help of our friends Dave & Michele, Ken, and hardrock Andy
just in time for fall. Photo by Tina Veldkamp. |
Another
view of the south side of the house from halfway down the driveway to the
lake. Photo by Tina Veldkamp. |